About this document
Purpose
Record what must change after a baseline, why, what else it touches, and who decided.
When to use
Any time after a baseline, before anything is changed. Inputs: the traceability matrix and the source register. Feeds: the decision log, the new baseline and the traceability matrix.
How to fill it in
- Say what changes and what triggered it, with the source.
- Filter the traceability matrix on the items the change touches, and list every affected item by its ID.
- Say what happens if nothing is done.
- Weigh at least two options, doing nothing among them.
- Record the decision, the date and who decided, with the decision log entry.
- Update the affected documents, and note the new version of each.
What a reviewer will ask
- What exactly changes, and what triggered it? Answered in CR-01, "Trigger and source": SRC-10 set 30 September 2026 for a change that SRC-07 had already made.
- What else is affected? Answered in CR-01, "Impact": 14 documents, item by item, found through the matrix in 19.
- What happens if we do nothing? Answered in CR-01, "If we do nothing": every refusal notice from 30 September 2026 would name a body that no longer exists.
- Who approved it, and what is the new baseline? Answered in CR-01, "Decision" and "After approval": STK-06 on Friday 18 September 2026 (DEC-15); version 1.1 of each affected document, issued on Tuesday 22 September 2026.
- Why is a request deferred rather than approved or rejected? Answered in CR-02, "Decision": deferred until OQ-01 is answered (DEC-16). "Options" gives the earliest date it can come back, Friday 9 October 2026.
Common mistakes
- A change request with no impact analysis. You can spot it when the impact section names documents but no items.
- Approval before the impact is known: the decision is dated before the impact table was complete.
- The trace not updated afterwards: the matrix still shows the old rows after the change is closed.
- Changes made quietly, without a request: a document's version moves, and no change request explains it.
- A deferred request with no condition for its return: nobody can say what would bring it back.
Why it looks like this
- Two requests in one file, one approved and one deferred, because a deferral is a decision too (DEC-16). Rejected: logging approved changes only, which would lose CR-02's impact analysis until someone raised it again.
- The impact table lists items by ID, found by filtering the matrix in 19 on BR-41, BR-53 and BR-60. Only then does it say which document holds each. Rejected: a list of documents, which says where to look but not what to change.
- CR-01's timeline shows what was known when. SRC-07 was in the register at the baseline, with no date. SRC-10, made on the day of the baseline, set the date, so it joined the register in version 1.1 with the next free number. Rejected: adding SRC-10 to the baseline after the event, which would hide that the baseline missed it.
- Glossary terms, clock states and parts of the brief carry no ID, so they appear in the impact table by name. Rejected: leaving them out because the matrix cannot see them.
This document is in the full set
You are reading the About page. The filled and blank versions, the files and the links between IDs open after purchase.
3 sections in the filled version · 6 pages
- Document control
- CR-01 Name the regulator the Information Commission
- CR-02 Retire dormant social media accounts
19 documents online and 56 files in one ZIP. 14 days to ask for a refund, no questions asked.
Free to read now: 03 Project brief and 21 Review exercise.
Files for this document
- 20-change-request-filled.docx 44 KB In the full set
- 20-change-request-blank.docx 40 KB In the full set